Owasso Road Construction 2026: Local Street Timelines

"The drive into Owasso is just absolutely awful," Connor West told KTUL in August. He is a mechanic at Precision Diesel Performance and spent months working beside the US-169 construction. "It was a lot worse before they went to extending it to three lanes. Now that it's three lanes, it's going to be a lot better."

The highway is now the finished part of Owasso's road work. The orange barrels have moved onto the surface streets. Garnett Road, the 106th and 129th intersection, and the 96th and 145th intersection will carry the construction into spring 2027. All three are being rebuilt to the same standard, with wider lanes plus sidewalks, bike lanes and trails along roads that never had them.

Where each project stands in early October

Several of these finish dates have moved since summer, so the table below uses the most recent date each source gives.

Corridor Started Current status Expected finish
US-169, 66th to 86th St N Scheduled for February 16, 2026 Complete, all lanes open Finished August 2026
Garnett Rd, 106th to 116th St N September 8, 2025 Traffic on new lanes from 106th to 112th City: November 2026. KJRH: December 2026, with sod into early 2027
E 106th St N and N 129th E Ave March 16, 2026 Behind schedule, bridge box underway March 2027
E 96th St N and N 145th E Ave August 17, 2026 Early phase, temporary lanes Final completion May 14, 2027
Ranch Creek Trail Not yet Design through December 2026 Construction early 2027

US-169 left one new habit to learn

The last stretch of the 169 widening from 66th to 86th involved nighttime ramp closures and paving. KRMG reported that all northbound lanes were expected to reopen August 10 and southbound lanes August 11. By August 18, KTUL confirmed that all three northbound lanes were open.

The change drivers feel most is just past 86th Street North. Northbound drivers continuing past the intersection now need the left two lanes, because the far-right lane is exit-only for 86th. KTUL reported that last-second lane changes there had already caused several close calls. Carter Barnett, another Precision Diesel mechanic, said he was grateful crews got it done "in a timely manner" but still had questions about whether the new layout would hold up as traffic grows.

That question about growth also explains the work on the surface streets. A wider highway only helps if the arterials feeding it can move cars, and Owasso's arterials are where the City is spending now.

Garnett Road is the clearest preview of the new standard

The stretch of Garnett between 106th and 116th is going from two lanes to five. The City's bid scope lists a concrete roadway, new storm sewers, sidewalks and trails, fiber conduit, water and sewer work, removal of a lift station, and a double-cell box bridge. R&L Construction holds the contract, which the City Council approved in July 2025.

Most of the change is in what gets added alongside the lanes. Travis Blundell, Owasso's assistant Public Works director, described the policy to KJRH:

"No, there were not sidewalks there before. Anytime Owasso has been putting in new roadways, new five-lane roads, we've included bike lanes, five-foot sidewalks, and a five-foot multi-purpose trail. That's to accommodate many modes of travel; obviously biking, walking, or running."

As of the City's August 19 progress note, the contractor had shifted traffic onto the new concrete lanes from 106th to 112th and was moving paving crews back to 106th to start the northbound lanes. Work on the bridge, subgrade and underground infrastructure was ongoing. The southern half of this stretch already drives on new pavement while the other side is still being built.

Garnett from 96th to 106th, just to the south, was already finished. A City report from March 2025 listed that roadway as complete, at an estimated $12,656,722. Of that, $9,456,722 came from Owasso's one-cent sales tax and $3.2 million from other funding. The same report put the 106th-to-116th segment at $12,745,981, all from the one-cent sales tax. Those are early-2025 estimates. Neither the City's status sheet nor the public bid posting gives an awarded contract figure.

The businesses on the road are waiting for the finish. Shirley and Jody, who run Shirley and Jody's Daylight Donuts near the construction, told KJRH that traffic there has sometimes been bumper to bumper. "It'll pick up tremendously because people will be able to drive wherever they need to go now," Jody said. "They won't be stuck in two lanes."

New building along the road is moving at different speeds. The City's September 1 development report lists Chicken Express at 9331 N. Garnett Road as under construction, with no opening date. A site at the southeast corner of 96th and Garnett is also under construction, with no tenant named. German Corner Commercial, at the southwest corner of 116th and Garnett, is marked on hold.

The 106th and 129th intersection has moved into 2027

The 106th and 129th intersection is a four-way stop, and it will get traffic signals. KJRH reported in March that the plans include dedicated left- and right-turn lanes. News On 6 reported at the time that drivers should expect narrowed lanes, changing work-zone patterns and a 25 mph speed limit.

The timeline is the part that has changed. The City's September 1 status sheet still listed December 2026, with crews installing reinforcing steel at the floor of the bridge box. By September 26, KJRH reported that the City now called the project behind schedule but on budget, with completion expected in March 2027.

Earl Farris, Owasso's project administrator, explained what the signal will change. "Drivers will have traffic signals that allow traffic to move through more freely, and it's going to clear traffic from all directions much faster, so we shouldn't have backups," he told KJRH. "It's also going to be much easier to make turns at the intersection."

Rejoice Christian School sits right next to the intersection. Katie Dewey, its head of communications, said in a statement that the work had not significantly affected drop-off or dismissal, and called it "short-term pain for long-term gain."

This intersection is the first piece of a longer plan. News On 6 reported that the 106th corridor out to 145th would be widened from two lanes to four, with medians, lighting, sidewalks and a trail. The City's September sheet lists engineering design for the segment from 129th to 145th as 90% complete.

96th and 145th just started, and its phases are mapped out

On the east side of town, the 96th and 145th intersection is at the start of its schedule. Diversified Civil Contractors won the contract in May 2026, and construction began August 17. The City's August public-meeting presentation lays out the sequence:

  1. Contractor mobilization on August 17
  2. Temporary pavement for Phase 1 on August 24
  3. Phase I construction beginning September 1
  4. Substantial completion on April 14, 2027
  5. Final completion on May 14, 2027

The temporary lanes on 145th will be built on the west side while the permanent roadway goes in on the east side. The City issued that clarification after an incorrect statement at the meeting. The finished intersection will be signalized, with two through lanes on 96th, left-turn lanes in both directions, sidewalks, pedestrian crossing signals, bike lanes and a multipurpose trail.

This is the same mix of lanes, sidewalks and trail that Blundell described for Garnett, now planned for the opposite side of town.

What comes after spring

The 96th and 145th intersection is followed by the stretch of 96th between 134th and 145th. Utility relocation there began in April 2026 and is scheduled to run through May 2027. AEP/PSO has finished its share, ONG was scheduled to start in late summer 2026, and AT&T in early fall 2026. Roadway construction is expected to begin in late summer 2027.

Two more corridors are in design. 96th Street from Mingo to Garnett is at 60%, and 86th Street from Main to Garnett is also at 60%, with land acquisition coming next. Construction on the Sports Park drainage improvements began in August, with final completion expected in January 2027.

Ranch Creek Trail is next for people on foot or bike. The City approved a land purchase agreement in December 2025. Design is scheduled to finish in December 2026, with construction in early 2027. The City bought 187 acres for the trail system near 76th Street North and Mingo. A 2023 City trail plan describes Ranch Creek as a future connection from McCarty Park toward the Mohawk Trail and Bikeway. That route is still a proposal.

For the latest phase on any of these corridors, the City posts monthly updates on its Project Status Report page. The September edition shows Garnett traffic already on its new lanes. It still lists December 2026 for the 106th and 129th signal, a date KJRH's September 26 report has since pushed to March 2027.

If you own a home on Garnett, 106th or 96th and are thinking about when to list, or you are considering a home near one of these intersections and want to know how the construction schedule fits your timing, Philip Shain can go over the dates with you, corridor by corridor. Let's Connect.